When to Use This Checklist
- Step 1: Ask What's NOT Included Before You Ask the Price
- Step 2: Compare Shaw vs Mohawk on Paper, Not Just Price
-
Step 3: Coordinate Flooring with the Right Butcher Block Countertop
-
Step 4: Pay for Realistic Shipping (Save Money Later)
- Step 5: How to Roll a Joint (A Flooring Seam, That Is)
-
Step 6: Add Waste to Every Flooring Order
-
Step 7: Inspect Everything Before the Installer Arrives
-
Common Mistakes I Still Catch on Jobs
-
Final Thought
I've been ordering flooring for a commercial renovation company for eight years. By my own count, I've made 14 serious mistakes in that time—mistakes that cost roughly $3,200 in wasted material, rush fees, and rework. This checklist is the one I wish someone had handed me before my first Shaw order. It's built around the screwups I actually lived through.
If you landed here because you searched shaw motors or boston scally cap: this article is about Shaw flooring, not cars or hats. Fair warning. Keep reading if you're buying floors, though.
When to Use This Checklist
Use this before you approve a quote, place an order, or let an installer on site. I wrote it for contractors, designers, and anyone who buys flooring for a living—but homeowners doing their own renovation will pick up a few things too. There are seven steps, plus a list of mistakes I still catch on jobs today.
Step 1: Ask What's NOT Included Before You Ask the Price
I've learned to ask what's not included before I ask for the total. On a 5,000-square-foot Shaw carpet order, the quoted price looked great. Then came delivery, removal of old carpet, stair metal, transition strips, glue, and a fee for moving furniture. The real cost was 22% higher than the number on the quote. It wasn't that the supplier was trying to trick me—I just never asked.
The Questions I Ask Now
- Delivery and staging
- Old flooring removal and disposal
- Stairs, transitions, and trim
- Adhesive, underlayment, and vapor barrier
- Moving furniture or appliances
The vendor who lists all fees upfront—even if the total looks higher—usually costs less in the end. For reference, my January 2025 Shaw LVP order came to $3.10 per square foot for materials, excluding installation. That's just one data point; verify the current price before budgeting.
Step 2: Compare Shaw vs Mohawk on Paper, Not Just Price
You can't get far into a flooring search without seeing the shaw vs mohawk carpet debate. I've installed both. Neither brand is universally better. The winner depends on the specific product line, the warranty, and how the distributor treats you.
I almost chose a Mohawk carpet for one job because it was 15% cheaper on the spreadsheet. My gut said the Shaw rep had been quicker with answers, but the data pointed to Mohawk's face weight. I went with my gut. A month later, Mohawk's delivery date slipped by 10 days. The savings disappeared when I paid our crew to stand around.
What I Compare Instead
- Face weight and density for carpet
- Wear layer thickness for LVP
- Warranty terms, especially for commercial use
- Pattern repeat and how much extra material it demands
Transparency goes both ways: ask the supplier what happens if the timeline slips.
Step 3: Coordinate Flooring with the Right Butcher Block Countertop
If your project includes a kitchen, don't pick flooring and butcher block countertops in separate silos. I made that mistake. I matched a warm red-oak butcher block with a cool gray carpet. The two materials fought each other, and the homeowner noticed before the installers packed up.
Now my checklist includes a sample check:
- Hold the countertop and flooring samples side by side in natural light.
- Look at undertones—warm vs. cool—not just the base color.
- Decide whether you want contrast or a seamless match.
- Check the cabinet color too, because butcher block steals the show.
This isn't about being fancy. It's cheaper to move samples around than to reorder.
Step 4: Pay for Realistic Shipping (Save Money Later)
I saved $80 once by choosing standard shipping on a flooring order. It felt like a win. Then the material didn't show up until the crews were already on site. I spent $400 on a rush reorder of matching product, plus overtime for the crew. The $80 I saved cost me roughly $480. I still wince thinking about it.
Shipping is not the place to optimize the cheapest line item. Ask for the vendor's commitment by date, not just a promise. If they won't guarantee delivery, build in a buffer or pay for expedited service. Getting the job done on time matters more than a small shipping discount.
Step 5: How to Roll a Joint (A Flooring Seam, That Is)
Yes, that heading is a trap. I'm talking about rolling a seam with a seam roller—the boring, unglamorous step that prevents many callbacks. In my first year, an installer told me to always roll the joint after seaming. I nodded, didn't do it, and the seam lifted within a week. $800 of carpet went straight to the trash. That's when I believed him.
Seam Rolling Basics
- Press the seam tape and adhesive exactly as the manufacturer says.
- Run the seam roller along the joint with steady pressure.
- Roll it twice—once in each direction, if the tool allows.
- Wait the specified time before trimming or walking on the seam.
Do not skip this to save five minutes. And if you wear a boston scally cap on site like I do, spin it backward while you lean over the adhesive. I ruined a good cap that way.
Step 6: Add Waste to Every Flooring Order
My biggest ordering mistake: I calculated the room square footage perfectly and ordered exactly that much Shaw patterned carpet. I forgot about pattern matching and room shape. The installer had to cut around a corner, and I didn't have enough to continue the pattern into the hallway. The reorder cost me around $670—though I might be misremembering the exact number because I've tried to block it out.
The fix is simple:
- Add 5–10% waste for straight layouts.
- Add 10–15% for diagonal or patterned installations.
- Check that every carton comes from the same dye lot.
That last one is easy to miss until the floor looks patched.
Step 7: Inspect Everything Before the Installer Arrives
I once scheduled an install and didn't open the cartons until the crew was there. Twenty-three cartons were from a different dye lot than the rest. The color shift was subtle in the box and obvious on the floor. We had to stop, reorder, and delay the owner's move-in date.
Now inspection is part of my pre-install checklist:
- Photograph the label on every carton.
- Confirm matching dye lots and batch numbers.
- Open random cartons and look for crushed edges or scrapes.
- Note any damage on the delivery receipt before signing.
When I do this, suppliers get quieter about hidden extras. A vendor that belongs on the quote usually belongs on the project.
Common Mistakes I Still Catch on Jobs
A few items didn't fit neatly into the seven steps, but they cause callbacks every year:
- Skipping the moisture test before gluing LVP to a concrete slab.
- Underestimating the cost of moving heavy furniture, especially up stairs.
- Forgetting transition strips at room openings. Each one adds up.
- Not letting flooring acclimate in the room for 48 hours before install.
Acclimation sounds like a formality until the planks expand and buckle.
Final Thought
This checklist isn't perfect. I wrote it because I needed it, not because I have it all figured out. It's helped my team catch 47 potential errors over the last 18 months. If you take away just one thing, let it be this: ask what's not included before you approve a quote. The upfront number rarely tells the full story.
Oh, and one more thing I should mention: every job is different. When in doubt, call the manufacturer's tech line before you install. It's cheaper than a reorder.